Completed Project Milestones
November 1, 2007 NEPA Environmental Public Hearing
April 21, 2008 Charlottesville City Council Public Hearing
August 18, 2008 Council Selection of Preferred Alternative
October 29, 2009 Design Public Hearing
December 7, 2009 City Council Design Approval
August 2010 VDOT Design Public Hearing Approval
December 18, 2012 FHWA Approved & Authorized Project for Advertisement
January 25, 2012 Right of Way Authorization
Spring 2012 Advertisement
March 4, 2012 Begin Construction
Future Project Milestones
Summer 2015 Complete Construction

 