Interchange Reports:

Interchange Report as of December 10, 2014

The 250 Interchange Project is 92.1% complete

Estimated Completion – Summer 2015

The previous two weeks (12/8-12/19), the contractor has been:
  • Placing reinforcing steel and concrete for bridge approach on Abutment B
  • Completing deck pour for bridge
  • Completed 250 east of bridge
  • Reconstructing the Dogwood Memorial
  • Reconfiguring/reconstructing CARS parking lot
  • Installing drainage structures/pipe/curbing throughout project
  • Performing signal work
  • Installing landscaping throughout project
The following two weeks (12/22-1/2), the contractor will be:
  • Continuing work on Bridge & Abutment B – constructing parapets
  • Competing signal work
  • Installing final signage
  • Installing storm water system along project
  • Continuing reconstruction of Dogwood Vietnam Memorial

Interchange Report as of October 10, 2014

The 250 Interchange Project is 88.9% complete

Estimated Completion – Summer 2015

The previous two weeks (10/27-11/7), the contractor has been:
  • Installing  Bridge Deck and Abutment B
  • Placing Backfill behind Abutment B
  • Grading slopes and placing fill/seed/mulch
  • Reconstructing the Dogwood Memorial
  • Installing drainage structures
  • Placing curbing/sidewalk throughout project
  • Constructed ramp from McIntire to 250EB
  • Paving ramp to 250EB, Birdwood Avenue and Shared Use Paths
The following two weeks (11/10-11/21), the contractor will be:
  • Completing traffic shift of 250EB onto Ramp
  • Continuing work on Bridge & Abutment B
  • Installing storm water system along project
  • Constructing sidewalk and shared use paths
  • Continuing reconstruction of Dogwood Vietnam Memorial

Interchange Report as of September 10, 2014

The 250 Interchange Project is 85.4% complete

Estimated Completion – Summer 2015

The previous two weeks (10/13/-10/24), the contractor has been:
  •         Installing  Bridge Deck and Abutment B
  •         Placing Backfill behind Abutment B
  •         Grading slopes and placing fill/seed/mulch
  •         Reconstructing the Dogwood Memorial
  •         Installing drainage structures for new 250
  •         Placing curbing/sidewalk throughout project
The following two weeks (10/27-11/7), the contractor will be:
  •         Continuing work on Bridge & Abutment B
  •         Constructing ramp from McIntire to 250EB
  •         Installing storm water system along project
  •         Constructing sidewalk and shared use paths
  •         Continuing reconstruction of Dogwood Vietnam Memorial

Interchange Report as of September 10, 2014

The 250 Interchange Project is 85.4% complete

Estimated Completion – Summer 2015

The previous two weeks (9/22-10/3), the contractor has been:
  • Installing  Bridge Deck and Abutment B
  • Activated new signal @ Harris/McIntire
  • Grading slopes and placing fill/seed/mulch
  • Completed new culvert under 250
  • Reconstructing the Dogwood Memorial
  • Constructed trailhead parking lot
  • Installing median along McIntire
  • Completed waterline across 250
  • Installing storm water system along McIntire
The following two weeks (10/6-10/17), the contractor will be:
  • Continuing work on Bridge & Abutment B
  • Reconfiguring curbing/asphalt of McIntire Road between Harris and 250
  • Installing storm water system along project – McIntire, Park Street ramps
  • Constructing sidewalk along Birdwood
  • Continuing reconstruction of Dogwood Vietnam Memorial
  • Installing signals @ Park Street/ramps

Interchange Report as of August 10, 2014

The 250 Interchange Project is 78.6% complete

Estimated Completion – Summer 2015

The previous two weeks (9/8-9/19), the contractor has been:
  • Constructing utility duct bank along 250EB
  • Installing  Bridge Deck and Piling Abutment B
  • Installing signals @ Park Street/ramps and Harris/McIntire
  • Grading slopes and placing fill/seed/mulch
  • Completed new culvert under 250
  • Reconstructing the Dogwood Memorial
  • Completed trailhead parking lot
  • Installing waterline across 250
  • Removing curb and asphalt along McIntire
The following two weeks (9/22-10/3), the contractor will be:
  • Continuing work on Bridge & Abutment B
  • Reconfiguring curbing/asphalt of McIntire Road between Harris and 250
  • Continuing reconstruction of Dogwood Vietnam Memorial
  • Installing signals @ Park Street/ramps and Harris/McIntire
     

Interchange Report as of August 10, 2014

The 250 Interchange Project is 78.6% complete

Estimated Completion – Summer 2015

The previous two weeks (8/25-9/5), the contractor has been:
  • Constructing utility duct bank along 250EB
  • Completing gas line relocations for project
  • Installing  Bridge Deck
  • Switching SB McIntire Road traffic to permanent location
  • Working on Shared Use Paths along McIntire
  • Graded for new sidewalk and to reconstruct Harris/McIntire Intersection
  • Removing existing culvert under 250 & installing new culvert under 250
  • Started reconstruction of Dogwood Memorial
The following two weeks (9/8-9/19), the contractor will be:
  • Continuing work on Bridge & Abutments
  • Completing new culvert under 250
  • Reconfiguring curbing/asphalt of McIntire Road between Harris and 250
  • Continuing reconstruction of Dogwood Vietnam Memorial
  • Installing new waterline across 250
  • Installing signals @ Park Street/ramps and Harris/McIntire

Interchange Report as of August 10, 2014

The 250 Interchange Project is 78.6% complete

Estimated Completion – Summer 2015

The previous two weeks (8/11-8/22), the contractor has been:
  • Completed Ramp 2 Retaining Wall – new 250EB on ramp @ McIntire
  • Erected steel girders for Bridge
  • Continued work on Abutment Wings for Bridge
  • Worked on Shared Use Paths along McIntire
  • Graded for new sidewalk and to reconstruct Harris/McIntire Intersection
  • Installed gas line on 250EB
  • Completing signal installation at McIntire/Harris and McIntire/250EB intersections
  • Removing existing culvert under 250
The following two weeks (8/25-9/5), the contractor will be:
  • Continuing work on Bridge & Abutment Wings
  • Installing signals @ Park Street/ramps and Harris/McIntire
  • Paving McIntire/Harris intersection
  • Starting reconstruction of Dogwood Vietnam Memorial
  • Installing new waterline across 250

Interchange Report as of July 10, 2014

The 250 Interchange Project is 75% complete

Estimated Completion – Summer 2015

The previous two weeks (7/28-8/8), the contractor has been:
  • Forming & Backfilling Ramp 2 Retaining Wall – new 250EB on ramp @ McIntire
  • Creating Abutment Footers and Forming Abutment Wings for Bridge
  • Working on Shared Use Paths along McIntire
  • Installing gas line on 250EB
  • Installed junction boxes at McIntire/Harris and McIntire/250EB intersections
  • Completed stream diversion for culvert under 250
The following two weeks (8/11-8/22), the contractor will be:
  • Installing steel girders for Bridge
  • Installing signals @ Park Street/ramps and Harris/McIntire
  • Continuing work on Bridge Abutments
  • Continuing work on Ramp 2 Retaining Wall – new 250EB on ramp @ McIntire
  • Completing gas line along 250EB
  • As of July 10, 2014, Interchange project is 75% complete.
  • Estimated Completion – Summer 2015.

Interchange Report as of July 10, 2014

The 250 Interchange Project is 75% complete

Estimated Completion – Summer 2015

Previous two weeks (7/14-7/25) the contractor has been:
  • Forming Ramp 2 Retaining Wall – new 250EB on ramp @ McIntire
  • Switched traffic along 250EB to complete culvert under 250
  • Completed curb for McIntire/Harris Intersection
  • Forming wing footer for bridge
  • Installing signals @ Park Street/ramps and Harris/McIntire

The following two weeks (7/28-8/8) the contractor will be:

  • Installing signals @ Park Street/ramps and Harris/McIntire
  • Continuing work on Bridge wing walls
  • Continuing work on Ramp 2 Retaining Wall – new 250EB on ramp @ McIntire
  • Relocating gas line along 250EB

Interchange Report as of June 10, 2014

The 250 Interchange Project is 72% complete

Estimated Completion – Summer 2015

Previous two weeks (6/30-7/11) the contractor has been:
  • Installing Curbing and Paving on new section of 250 EB/WB (west of McIntire Road)
  • Installing drainage structures @ 250 & McIntire
  • Driving remaining piles for Bridge Abutment Wings
  • Forming Ramp 2 Retaining Wall – new 250EB on ramp @ McIntire
The following two weeks (7/14-7/25) the contractor will be:
  • Installing signals @ Park Street/ramps and Harris/McIntire
  • Continuing work on Bridge Abutments
  • Continuing work on Ramp 2 Retaining Wall – new 250EB on ramp @ McIntire
  • Creating detour for 250EB @ McIntire so work can continue on culvert under 250